Power utility Eskom announced on Wednesday that due to the continued delays in returning generation units to service at Kusile, Tutuka, Duvha, Kendal and Koeberg Power Stations, Stage 2 loadshedding will be implemented from 10:00 today until 22:00 on Sunday night.
“In addition, these constraints have been exacerbated by the high winter demand throughout the day over the past few days as brought about by the colder temperatures.”
Eskom said breakdowns currently total 13 752MW of capacity, while planned maintenance is 1 273MW of capacity.
“These capacity constraints will continue for the foreseeable future and all South Africans are urged to reduce their use of electricity, particularly between 17:00 and 22:00, when the winter demand is the highest.”
Eskom said it will communicate promptly should there be any changes.